27th July 2010: Retrofit Works Update


The tenant is now away on holiday, last week she moved a lot of her possessions and furniture into the temporary store and did a tremendous job so that the contractors were left with more than adequate room to manoeuvre.


The kitchen units containing the sink and washing machine space were removed and part of the rear and bathroom walls were found to be damp, this accounts for the musty smell in the cupboard the resident had commented on. Croydon Council attended in the afternoon as arranged to inspect and a way forward was agreed, we are now installing the raised flooring and shall be refitting the units.

The bath was also discussed; consensus of opinion is to leave in it position installing the insulation as planned. When the insulation, underfloor heating and new flooring is completed the bath edge will be lower.


The spacetherm pp was delivered yesterday, an interesting material, it’s worth a look (see picture above).

Rod Selby
Jenner Contractors