Tuesday, 19 October 2010

Week 12 Report - 15th October 2010


We are now on the home run, the scaffolding has been fully struck this week and the Thermal Reflections system is being installed. Apart from works to fit the internal wall insulation in the main bedroom, the internal works are in the final stages.

Discussions have been taking place regarding storage because the works have resulted in the loss of some of the existing space. The installation of slatted shelving in the reconfigured airing cupboard in envisaged as well as fitting some shelves in the under stairs cupboard.

Photos show the building without the scaffolding and the 2 panels that were installed on Friday.

The improvement internal comfort levels are now very noticeable and this is without the under floor heating in operation. The roof PV panels continue to silently generate electricity - it’s also most magic!

Monday, 11 October 2010

Week 11 Report - 8th October 2010

Again the weather has frustrated progress on the external insulation works with 3 days lost. Works resumed at the end of the week and application of the top coat is scheduled for Monday and Tuesday next week. Furthermore, the new highly thermally insulated front door has now been installed.

The finishing’s to the kitchen and bathroom areas are now being progressed with the new floor coverings be laid on Friday and decorations in the process of being made good. Following discussions it was agreed to relocate one of the base units to improve the layout of the kitchen, the change will allow the fridge freezer to be more conveniently positioned.

On Monday and Tuesday the damp proofing works to the under stairs cupboard were undertaken. These additional works entailed the removal of the existing wall finishing’s, damp proof chemical injection and then re-plastering.

Wednesday, 6 October 2010

Week 10 Report - 1st October 2010


The living room has now been handed back and the improved comfort level of the room is noticeable. The Spacetherm to the internal face of the front wall and the external insulation on the side wall is having the desired effect.

The remaining areas of under floor heating have been installed and as predicted the kitchen, bathroom and WC were time consuming. We are now looking forward to the installation of the Thermodynamic Block and Solar Panels which will supply the heating and hot water.

Unfortunately the weather has continued to frustrate the progress of the external wall insulation; however the long awaited external doors supplied by Masterdor have now been installed. Some progress has been possible.

The PV panels continue to generate “free” electricity as the photo testifies, regularly monitoring the readings has become a bit of an obsession. I really think I need to get out more!

Monday, 4 October 2010

Week 9 Report - 24th September 2010


Works to the living room continued this week with the wall papering and decorations. New laminate flooring has been obtained and will be fitted on Saturday enabling the room to be handed back to the Resident on Monday.

The remaining areas of under floor heating will be installed next week, these being the kitchen, bathroom and WC. These smaller areas are more intricate and time consuming to install, once completed a very disruptive element of the works will be behind us.

Works to install the external wall insulation system is now underway, unfortunately the weather has not been favourable and time has been lost. This weeks photos show the external walls after they had been “washed” prior to the fixing of the insulation boarding, with the grime removed they looked crisp and almost newly painted.