Week 12 Report - 15th October 2010


We are now on the home run, the scaffolding has been fully struck this week and the Thermal Reflections system is being installed. Apart from works to fit the internal wall insulation in the main bedroom, the internal works are in the final stages.

Discussions have been taking place regarding storage because the works have resulted in the loss of some of the existing space. The installation of slatted shelving in the reconfigured airing cupboard in envisaged as well as fitting some shelves in the under stairs cupboard.

Photos show the building without the scaffolding and the 2 panels that were installed on Friday.

The improvement internal comfort levels are now very noticeable and this is without the under floor heating in operation. The roof PV panels continue to silently generate electricity - it’s also most magic!