A site visit by CEN on the Wednesday of week 2 saw the successful demolition of the porch to make way for the new sun trap – a highly glazed porch to add solar gain and natural daylighting to the property.
The new hot water cylinder and upstairs pipework was also being installed.
The resident was getting on well with the workmen and seemed pretty happy providing dust was kept to minimal levels and that doors remained closed to prevent dust getting inside the house.