Wednesday, 18 August 2010
13th August 2010: Week 3 Update
This week the scaffolding was erected in preparation for the roofing work and to facilitate the window replacement. The two Scaffolders were very considerate and courteous to the resident who was at home the day the scaffolding was erected.
The roof works require the removal of the existing slating, battening and felt to install the insulation board between the rafters.
This work is obviously weather sensitive as would be any domestic re-roofing project. Installing the insulation from the outside was chosen to avoid the major disruption that would occur with the removal and reinstatement of the existing internal sloping and horizontal ceilings.
During this operation the in-roof PV panels are to be installed.
The existing windows were replaced this week with the new high performance units as can be seen from the attached photos. With the new windows in place the installation of the Spacetherm wall boarding can commence, this is likely to be a relatively slow process requiring careful handling to keep dust levels to a minimum.