Week 5 Update: 27th August 2010


The roof works were completed early in the week ahead of the torrential rain that was experienced. On a positive note the new roof coverings and PV panel passed this impromptu testing. The internal electrical installation for the PV panels was fitted ready for commissioning early next week.

With completion of the roof works the top lift of scaffolding can be struck and the external insulation commence. Prior to this a final inspection is to be made and any minor items dealt with. In preparation for the external insulation the rear and side walls below ground level have been further exposed.

Again the internal works continued with the finishing and decorating of the Spacetherm wall boarding that has been installed in the dining room. The making good and decorating of the reconfigured airing cupboard has been completed. As the Resident could not be left without hot water reinstatement had to be worked around the new equipment. Unfortunately the opportunity for the painter to have an empty cupboard to work on never arose.

Delivery of the German manufactured floor insulation panels has been confirmed for next Tuesday, this now enables the installation of the under floor heating and new flooring.

No comments:

Post a Comment