Week 6 Update - 3rd September 2010

The final inspection of the PV panels has been completed and they are now happily generating electricity. Painting of the fascia boards has been undertaken after completion of the roofing works.

The making good of the decorations to the dining room is now in hand. This has proved to more than was expected as the existing wallpaper cannot be matched, it has been agreed to strip of the existing and re-paper with new.

This is to be followed by the installation of the floor insulation, under floor heating and flooring.

All being well in the very near future will shall be handing the completed room back to the Resident.

Included in the photos this week are the German manufactured insulation panels.