Week 7 Update - 10th September 2010

This week has been pivotal with the removal of the top lift of scaffolding in preparation for the installation of the external insulation system. With the top lift of scaffolding out of the way it has been possible to photograph the PV panels from ground level. A photo is attached of the meter showing the units feed back so far.

Very good progress had been made on the dining room. The walls have been re-papered, the floor insulation laid, under floor heating fitted and the new flooring installed. The decorations and re-laying of the laminate flooring is to continue over the weekend and the room will be ready for Tuesday.


The completion of this first room will provide the resident with an undisturbed area were things can get back to normal.

Of other interest we have included photos of the resident’s roses which are spectacular, the photos do not do them justice; the garden is a feast for the eyes.