Thursday, 23 September 2010

Week 8 Report - 17th September 2010


The dining room was handed back to the resident on Tuesday which is a notable milestone. From the photos it can been that in this room things are returning to normal.

We have now moved on to the living room and in here there has been some unexpected works. With full access to the room an inspection was made by a damp and timber treatment specialist on Wednesday. They recommend improvements to the ventilation of the under floor void, this was work was undertaken and completed within 24 hours. Arrangements had been previously made for the under floor heating to be installed on Friday morning and postponement was not option.

The photos show the under floor heating during its installation on Friday.


Materials for the external wall insulation system were delivered to our yard on Friday and will be transported to site as progress requires. It can be seen that the volume of material is considerable and that storage on site was not option.